Full Construction Schedule | College of Arts & Sciences | Kent State University

Full Construction Schedule

Integrated Science Building

2015

  • October- Groundbreaking Ceremony
  • November- Excavation
  • December- Excavation, Foundations

2016

  • January- Foundations
  • February- Steel, Foundations
  • March- Concrete, Steel, Foundations
  • April- Concrete, Steel
  • May- Roofing, Concrete, Steel
  • June- Spray-On Fireproofing, Ductwork/Piping/Conduit, Roofing
  • July- Exterior Envelope, Spray-On Fireproofing, Ductwork/Piping/Conduit
  • August- Exterior Envelope, Ductwork/Piping/Conduit
  • September- Interior Framing, Exterior Envelope, Ductwork/Piping/Conduit
  • October- Interior Framing, Exterior Envelope
  • November- Interior Framing, Exterior Envelope
  • December- MEP Rough-In, Interior Framing

2017

  • January- MEP Rough-In
  • February- Drywall, MEP Rough-In
  • March- Drywall, MEP Rough-In
  • April- Final Landscaping, Finishes, Drywall
  • May- Final Landscaping, Finishes
  • June- Final Landscaping, Finishes
  • July-August- KSU move in to ISB
  • July-October- Parking Lot Alternate