August 2017
At a Glance
HIGH-LEVEL MILESTONES AND PROGRESS
Key Milestones |
Discovery |
Development |
Training /Testing |
Go-Live |
---|---|---|---|---|
Graduate Admissions
|
Completed
|
Completed
|
Completed
|
August 2016
|
CRM Architecture and Data Strategy
|
Completed
|
Completed
|
Completed
|
April 2017
|
UCM Marketing Cloud
|
Completed
|
Completed
|
Completed
|
May 2017
|
WKSU Marketing Cloud
|
Completed
|
Completed
|
Completed
|
May 2017
|
One Stop Discovery
|
Completed
|
N/A
|
N/A
|
May 2017
|
University Calendar - Phase I
|
Completed
|
Completed
|
Completed
|
June 2017
|
FLASHperks - Phase I
|
Completed
|
Completed
|
Completed
|
June 2017
|
Data Migration - General Person
|
Completed
|
Completed
|
Completed
|
July 2017
|
Duplicate Management
|
Completed
|
Completed
|
Completed
|
July 2017
|
Enterprise Marketing Cloud
|
Completed
|
Completed
|
Completed
|
July 2017
|
Recruiting - Phase I
|
Completed
|
Completed
|
In Progress
|
Final Go-Live Activities
In Progress
|
University Calendar - Rollout
|
Completed
|
In Progress
|
In Progress
|
August 2017
|
FLASHperks - Phase II
|
Completed
|
In Progress
|
In Progress
|
August 2017
|
Data Sync - General Person
|
In Progress
|
In Progress
|
Not Started
|
August 2017
|
Marketing Cloud for FLASHperks
|
In Progress
|
In Progress
|
Not Started
|
September 2017
|
CRM Architecture and Governance
|
In Progress
|
In Progress
|
In Progress
|
December 2017
|
Admissions
|
In Progress
|
In Progress
|
Not Started
|
April 2018
|