August 2017

 

At a Glance

HIGH-LEVEL MILESTONES AND PROGRESS

Key Milestones

Discovery 

Development 

Training

/Testing

Go-Live

Graduate Admissions
Completed 
Completed
Completed
August 2016
CRM Architecture and Data Strategy
Completed
Completed
Completed
April 2017
UCM Marketing Cloud
Completed
Completed
Completed
May 2017
WKSU Marketing Cloud
Completed
Completed
Completed
May 2017
One Stop Discovery
Completed
N/A
N/A
May 2017
University Calendar - Phase I
Completed
Completed
Completed
June 2017
FLASHperks - Phase I
Completed
Completed
Completed
June 2017
Data Migration - General Person
Completed
Completed
Completed
July 2017
Duplicate Management
Completed
Completed
Completed
July 2017
Enterprise Marketing Cloud
Completed
Completed
Completed
July 2017
Recruiting - Phase I
Completed
Completed
In Progress
Final Go-Live Activities
In Progress
University Calendar - Rollout
Completed
In Progress
In Progress
August 2017
FLASHperks - Phase II
Completed
In Progress
In Progress
August 2017
Data Sync - General Person
In Progress
In Progress
Not Started
August 2017
Marketing Cloud for FLASHperks
In Progress
In Progress
Not Started
September 2017
CRM Architecture and Governance
In Progress
In Progress
In Progress
December 2017
Admissions
In Progress
In Progress
Not Started
April 2018