HIGH-LEVEL MILESTONES AND PROGRESS

Key Milestones
Discovery 
Data Migrations
/Integrations
Custom Development 
(configuration, workflows)
Training
/Testing
Go-Live
Graduate Admissions Completed  In Progress In Progress In Progress
Application Live on 8/2
Decision Live on 8/24
Advancement Completed In-Progress Not Started Not Started March 2017
Recruiting/Admissions Completed In Progress Not Started Not Started April 2017
Student Retention In Progress Not Started Not Started Not Started April 2017
CCPD/WKSU 