February 2017


At a Glance

High-Level Milestones and Progress

Key Milestones
Discovery 
Data Migrations
/Integrations
Custom Development 
(configuration, workflows)
Training
/Testing
Go-Live
Graduate Admissions
Completed 
Completed
Completed
Completed
Application Live on 8/2
Decision Live on 8/23
Advancement
Completed
In-Progress
On Hold
On Hold
TBD
Recruiting/Admissions
Completed
In-Progress
In-Progress
Not Started
April 2017
Student Retention
Completed
In-Progress
Not Started
Not Started
Fall 2017
WKSU 
(Marketing Cloud)
Completed
N/A
In-Progress
In-Progress
TBD
One-Stop
In-Progress
In-Progress
In-Progress
Not Started
June 2017