November 2016
Key Milestones |
Discovery
|
Data Migrations
/Integrations
|
Custom Development
(configuration, workflows)
|
Training
/Testing
|
Go-Live
|
---|---|---|---|---|---|
Graduate Admissions | Completed | Completed | Completed | Completed |
Application Live on 8/2
Decision Live on 8/23
|
Advancement | Completed | In-Progress | In Progress | Not Started | TBD |
Recruiting/Admissions | Completed | In Progress | In Progress | Not Started | April 2017 |
Student Retention | In Progress | In Progress | Not Started | Not Started | April 2017 |
WKSU
(Marketing Cloud)
|
Completed | Not Started | In-Progress | In-Progress | TBD |