Are there phases to the project? | Summit Street Improvement Project | Kent State University

Are there phases to the project?

Yes. The project has been divided into phases to reduce the amount of impact to those who travel this stretch of roadway. The first phase, which included improvements to Summit Street from Fraternity Circle to Loop Rd, was completed in Decemer 2016.  The second phase, which will begin in March 2017, will improve Summit Street from Lincoln Street to Fraternity Circle.

During each phase one-way, one-lane, eastbound traffic will be maintained in the construction zones. Two-way, two-lane traffic will be maintained in all other areas of the project.