9/26- Cunningham Hall Renovation Updates
Work in Progress
- Continue sidewalk pouring and paver’s installation.
- Continue installation of stair treads ADA addition.
- Continue carpet installation.
- Complete duct work roughed in Human Anatomy Lab.
- Continue north side corridor curtain wall installation.
- Start cleaning operations.
Looking Forward
- Finalize paver’s installation.
- Finalize stair treads installation.
- Finalize carpet installation.
- Continue detailing work in basement, Human Anatomy Lab.
POSTED: Monday, September 26, 2016 - 9:38am
UPDATED: Thursday, January 19, 2017 - 9:05am