3/3- ISB Construction Updates
Work in Progress:
- Augarcast pile installation is complete.
- Grade beams and pile caps are ongoing. Currently complete along column line 1 on the North and working south.
- Started forming basement retaining wall along column line 1.
- Forming of Elevator #1 (North) hoistway walls has begun.
Looking ahead:
- Continue grade beam and pile cap installation working south.
- Pour basement retaining wall scheduled for 3/4/2016.
- Pour first lift of north elevator hoistway schedule for 3/8/2016.
POSTED: Thursday, March 3, 2016 - 3:25pm