Sciences Renovation | 1555958969 | Page 2 | Kent State University

Sciences Renovation

Work in Progress:

  • Completed first lift pour for elevator #2 (South).
  • Completed first lift pour for stair tower #3.
  • Grade beams and pile caps along column line 17 are complete.
  • Steel clips for sequence 1-4 are complete.
  • Steel erection for sequence 1-4 is in progress.

Looking forward:

  • Continue with the installation of the steel erection of sequences 1-4.
  • Form and pour lift #2 for elevator #2 (south).
  • Pour concrete basement retaining wall from column line 16 to 17B.

Work in Progress:

  • Continuing the steam and condensation piping in the East Mechanical room.
  • Heating and snow melt piping is continuing in the West Mechanical room.
  • Continuing with the chilled water piping in the West mechanical room.
  • Working on plenum duct at AHU-1 in East Mechanical Room.
  • Currently working on fiber data backbone.
  • Currently installing cable tray in tunnel.
  • Waterproofing of south wall continues.
  • CMU and elevator hoistway has begun.

Looking Forward:

Work in Progress:

  • Start forming elevator #2 (south).
  • Grade beam and pile caps along column line #17 between A and G is in progress.
  • Pile caps for elevator #2 are complete.
  • Installing pile caps for Stair #3.

Looking forward:

  • Steel erection sequence #1 will begin on Monday, April 18th.
  • Start forming stair #3 and be ready for first pour on April 22nd.
  • Continue with retaining wall to column line B-17.

Work in Progress:

  • Forming lift 3 on elevator #1.
  • Working on retaining wall progressing south to column line A7.
  • Pile caps and foundations for elevator #2 are complete.

Looking forward:

  • Pour lift #3 on elevator #1 on 4/8/2016.
  • Steel delivery and erection begins for sequence #1 on 4/11/2016 (North side – column line 0).
  • Continue with retaining wall south from column line A7 and turn east.
  • Start forming elevator #2 (south).

Work in Progress:

  • Pulling wire throughout for branch circuits.
  • Installing duct on 1st floor.
  • Complete domestic water rough-in on the 2nd floor.
  • Sanitary piping rough-in has been completed on the 3rd floor.
  • Completing remaining framing throughout.
  • Starting door frame installation.
  • Drywall delivery scheduled for 4/8/2016.
  • Steel delivery was 4/6/2016 and columns have been erected.

Looking forward:

  • Continue with steel erection.

Work in Progress:

  • Working on pile caps and grade beams.  Plan to start column line 17 (Southern most column line) next week.
  • Started working on forming elevator #2 (South).
  • Pouring elevator #1 second lift (North) today.
  • Continuing the installation of the basement concrete retaining wall along column line 'A' between A7 and A10.
  • Currently 45% complete with pile caps.

Looking forward:

  • Complete auger cast piles on column line 0 (North).

Work in Progress:

  • First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun.
  • Room 101 & 104 electrical rough-in is at 90% complete.
  • Machine Shop electric panel installed and completed on Saturday 3/19.
  • Room 223 electrical floor boxes are complete.
  • Currently core drilling for drains and water lines throughout the building.
  • Currently framing the 3rd floor restrooms and research lab.

Looking Forward:

Work in Progress:

  • Steam piping in the 3rd floor east mechanical room is 20% complete.
  • Steam condensate lines for the steam station and AHU#1 are in progress.
  • Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has begun.
  • Tie-in from AHU#1 to AHU#4 is in progress now that abatement is complete.
  • GMP C3 1st and 2nd floor ceiling tile removal is completed.

Looking Ahead:

Work in Progress:

  • New restroom plumbing rough-in nearly complete.
  • Sheet metal duct rough-in has begun on the first floor and the new restroom areas.
  • Electrical floor boxes are 75% complete in 223.
  • Sanitary drain and toilet carriers are complete in the second floor.
  • 3rd floor abatement for the restrooms is complete.
  • Poured the new addition floor slab was poured on 3/15/2016.

Looking ahead:

  • Continue with sheet metal duct installation on the first floor.

Work in Progress:

  • Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18.  Will be ready for cooling system startup on 4/15.
  • Currently insulating the chilled water pipes in the 3rd floor wast mechanical room.
  • Steam reducing station in the 3rd floor east mechanical room is approximately 10% complete.
  • Completed the installation of the temporary roof duct work.
  • Electrical demolition work in the tunnels is complete.