Work in Progress: Duct work on the 3rd floor is about 30% complete. Duct pressure testing is underway. Electrical disconnect and make safe are underway for the AHU's above the penthouse. Working on the steam pipe relocation on the second floor. Plumbing isolation valve replacement is complete throughout building. Fire suppression is about 90% complete. Exterior face brick and caps are complete. Flooring demolished in the lecture halls and the ceiling protection is in place in the planetarium. Selective demolition is in progress in the planetarium wing. Looking Forwar...