Sciences Renovation

ISB Work in Progress Continue pre cast and brick work along G line, lines 8 to 17. Continue curtain wall installation at the east side of the building. Continue monitor framing and glass at the north side of the building. Continue last back filling in the east section of the building. Last hydraulic slab pouring in the east...

Work in Progress Complete drywall work in basement, Human Anatomy Lab. Taping in Human Anatomy Lab is in progress. Continue north side corridor curtain wall installation. Continue cleaning operations. Looking Forward Continue detailing work in basement, Human Anatomy Lab. Continue north side corridor curtain wall installation. Start...

ISB Work in Progress Brick work along line 17, from B to G is in progress. Continue retaining wall along line 8. Continue curtain wall installation at the northeast side. Finalize pre cast and brick work along A line. Continue the pouring of the hydraulic slab on the east side, lines 14 to 17. CMU installation in penthouse completed. Start...

College of Arts & Sciences

Work in Progress Continue sidewalk pouring and paver’s installation. Continue installation of stair treads ADA addition. Continue carpet installation. Complete duct work roughed in Human Anatomy Lab. Continue north side corridor curtain wall installation. Start cleaning operations. Looking Forward Finalize paver’s installation. Finalize...

ISB Work in Progress Continue the work of water proofing mud mat on the east side of the building, lines 14 to 17. Continue framing roof work at east side of the building, and roofing work on the penthouse. Continue curtain wall installation at the northeast side. Continue backfilling for slab on grade from line 7 to 17. Continue pre cast and...

College of Arts & Sciences

Work in Progress: Duct work on the 3rd floor is about 30% complete. Duct pressure testing is underway. Electrical disconnect and make safe are underway for the AHU's above the penthouse. Working on the steam pipe relocation on the second floor. Plumbing isolation valve replacement is complete throughout building. Fire suppression is about 90%...

Work in progress: Temporary steam condensate line in tunnel is complete along with taps on main condensate and steam feeds for future connections. Chilled water line hangers are being installed above AHUs in Williams mechanical room. Steel erection in sequence 4 & 5. Steel detailing in sequence 2 & 3. Metal floor decking has begun in...

College of Arts & Sciences

Work in Progress: Fire alarm raceways are approximately 75% complete. Electric Panel 1J is complete. HVAC duct installation continues on floor 2 and 3. Temporary heaters have been removed from the building. HVAC curb delivered and set on 4/27. Door frame installation and drywall finishing happening throughout the building. Looking forward: ...

College of Arts & Sciences

Work in Progress: Forming basement retaining wall from column line 13G to 17C in progress. Forming of lift #2 at elevator #2 (south) for second pour is in progress. Forming of stair #3 is in progress. Concrete piers along column line B are in progress. Steel erection of sequence 1 - 4 are in progress. Steel detailing of sequence 1 is in...

College of Arts & Sciences

Work in Progress: Currently installing 1J electric panel, wire and raceways. Confirmed an electric shutdown will not be required now. Continuing to pull wire throughout. Continuing with HVAC sheet metal duct work on the 1st and second floor. Completing domestic water piping rough-in for drywall boarding. Framing continues for stairwell...