4/21- ISB/Williams Hall Construction Updates | College of Arts & Sciences | Kent State University

4/21- ISB/Williams Hall Construction Updates

Work in Progress:

  • Completed first lift pour for elevator #2 (South).
  • Completed first lift pour for stair tower #3.
  • Grade beams and pile caps along column line 17 are complete.
  • Steel clips for sequence 1-4 are complete.
  • Steel erection for sequence 1-4 is in progress.

Looking forward:

  • Continue with the installation of the steel erection of sequences 1-4.
  • Form and pour lift #2 for elevator #2 (south).
  • Pour concrete basement retaining wall from column line 16 to 17B.
  • Pour pile caps and grade beams along column line G.
  • Interior caps and grade beams along columns 9, 11, and 13 between A and C.
  • Form concrete basement retaining wall from 17B to 17C.
POSTED: Thursday, April 21, 2016 - 6:08pm
UPDATED: Thursday, January 19, 2017 - 9:05am