4/7- ISB/Williams Hall Construction Updates

Work in Progress:

  • Forming lift 3 on elevator #1.
  • Working on retaining wall progressing south to column line A7.
  • Pile caps and foundations for elevator #2 are complete.

Looking forward:

  • Pour lift #3 on elevator #1 on 4/8/2016.
  • Steel delivery and erection begins for sequence #1 on 4/11/2016 (North side – column line 0).
  • Continue with retaining wall south from column line A7 and turn east.
  • Start forming elevator #2 (south).
POSTED: Thursday, April 7, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM