5/12- ISB/Williams Hall Construction Updates
Work in Progress:
- Forming at stair #3 for 3rd lift continues; 2nd lift pour has been completed.
- Concrete piers along column line 'B' were completed.
- Steel erection in sequence 1 - 4 continues.
- Steel detailing in sequence 2 continues.
- Basement retaining wall between column line 17/A.1 to 17/C in progress.
- Steam, steam condensate and chilled water piping work in tunnel is in progress.
- Removal of temporary overhead protection at Williams Hall dock area.
- Chilled water line installation in Williams Hall mechanical room continues.
Looking forward:
- Start installation on steel sequence #5 & #6.
- Continue steel sequence #3 detailing.
- Continue work at elevator #2 for 3rd concrete pour.
- Complete forming for 3rd concrete pour next week.
- Continue utility work in tunnels.
POSTED: Tuesday, May 12, 2015 - 12:00am
UPDATED: Thursday, January 19, 2017 - 9:05am