2/25- Cunningham Hall Renovation Updates

Work in Progress:

  • Phoenix air valve replacement in the Annex research labs continues per schedule.
  • Continuing the chilled water piping in the 3rd floor east mechanical room.
  • Continuing the demolition of AHU#3.

Looking forward:

  • Complete the demolition of AHU#3 in the 3rd floor west mechanical room.
  • Mobilize the mason the week of 3/7/2016.
  • Continue Phoenix air valve replacement in the Annex.
  • Continue chilled water piping in the 3rd floor east mechanical room.
  • Steel submittals and manufacturing in progress.
  • Start tele/data duct bank layout.
  • Start excavation for footers and layout for basement foundation walls.
POSTED: Thursday, February 25, 2016 03:36 PM
Updated: Saturday, December 3, 2022 01:02 AM